Complete re-refurbishment of the college canteen and a series of toilet blocks, as well as a contemporary café extension and courtyard.
The refurbishment included new heating, lighting, ceilings, floors, windows and servery areas.
The canteen works were programmed for a compact 14-week period, starting in the summer half term and finishing in time for the start of term in September. It was therefore vital that the works were completed on time, in order that the canteen was open for when the students returned.
By working closely with the college, we were able to cause minimal impact and handover as scheduled. So fortunately, none of the students went hungry!